MANAJEMEN PROYEK SISTEM INFORMASI SI-47-06 [GDP]

Looking for MANAJEMEN PROYEK SISTEM INFORMASI SI-47-06 [GDP] test answers and solutions? Browse our comprehensive collection of verified answers for MANAJEMEN PROYEK SISTEM INFORMASI SI-47-06 [GDP] at lms.telkomuniversity.ac.id.

Get instant access to accurate answers and detailed explanations for your course questions. Our community-driven platform helps students succeed!

SPI=0.90 and AC=145000 and PV=100000 then CPI=?
0%
0%
0%
0%
View this question
if CPI 0.58 it means the project is ?
View this question
WPI (Work Performance Information) is an output in which process?
View this question
if SPI 1.95 it means the project is ?
0%
0%
0%
0%
View this question
Project is behind schedule if?
0%
0%
0%
0%
View this question
__________________ is a project performance measurement technique that integrates scope, time, and cost data.
View this question
Which of the following is not an output of the project cost management process called Estimate Cost?
View this question
Below are processes in cost management except
0%
0%
0%
0%
View this question
AC=100 and PV= 200 and EV=150 then SV=?
0%
0%
0%
0%
View this question
CPI=0.85 and AC=120.000 and PV=100.000 then SPI=?
View this question