Looking for BLDG2021-High Rise Bldg Construction (T3, 2025) test answers and solutions? Browse our comprehensive collection of verified answers for BLDG2021-High Rise Bldg Construction (T3, 2025) at moodle.telt.unsw.edu.au.
Get instant access to accurate answers and detailed explanations for your course questions. Our community-driven platform helps students succeed!
What is the accelerated ageing test of a façade system?
What is a disadvantage of the panellised façade system?
Besides their basic components, mobile cranes generally have _______ for increased stability.
The use of vision AI, such as Ailytics, can improve productivity and safety. However, this technology also has its challenges and limitations. Explain briefly four of challenges and limitations associated with the use of this technology.
A cast in-situ reinforced concrete wall is a type of exterior wall in a high-rise building. The tie holes in this type of wall must be adequately sealed after construction. What is the function of tie holes?
A 100-tonne crawler crane is required to lift a load 6.5m tall to a position 30 m above the surface on which the crane is operating, and 12 m away from the centre of the crane. The length and weight of the block, hook, and slings that are required to attach the hoist rope to the load are 7 m and 1800 kg respectively. The site layout requires the crane to pick up the load at a distance of 29 m from the centre of rotation of the crane. Based on table provided, determine the maximum load that can be hoisted.
A tower crane has a 50-m boom length and a two-rope pull hoist line. What is its maximum capacity at the 31-metre working radius based on the table below?
What is a disadvantage of using precast concrete panels as an exterior wall of a high-rise building?
The following statements about Project Remediate are correct, except:
Select all the correct disadvantages of using bricks as a wall in a high-rise building.