Which of the following statements about product backlog and sprint backlog are true and which are false?
During sprint planning the backlog items are chosen from the product backlog and placed on the sprint backlog.
The product backlog is the outcome of a development project.
Missing feature descriptions are first entered in the sprint backlog and at the end of a sprint they are transferred to the product backlog.