✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
A company has supplier’s lead time of 10 days and the number of days between reviews (review period or cycle) is 15. Which of the following is the standard deviation of demand over the review and lead time period if daily demand is 100 units and the standard deviation of daily demand is 10 units?