Based on the following project objectives given below, a.       advise an ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Based

on the following project objectives given below,

a.      

advise

an appropriate procurement system, and

(10

marks)

 

b.      

advise

its contractual relationships (you may use a diagram) to your Principal.

(10 marks)

Project Objectives:

Principal's Priority

5 Essential 

 

3 Desirable

2

1 Do Without

TIME:

Is early completion

required?

5

COST:

Is a firm price

needed before any commitment to construction is formed?

2

FLEXIBILITY:

Are variations

necessary after work has begun on site?

4

COMPLEXITY:

Is the building

highly specialised, technologically advanced or highly serviced?

5

QUALITY:

Is high quality

important?

5

CERTAINTY:

Is completion on

time important?

4

Is completion within

budget important?

2

DIVISION OF

RESPONSIBILITY:

Is single-point

responsibility wanted?

2

Is direct

professional responsibility wanted?

4

BUILDABILITY:

Is the early

contractor’s input important?

4