In projectmonitoring, what does a Schedule Performance Index (SPI) of 0.9 indicate?
In project
monitoring, what does a Schedule Performance Index (SPI) of 0.9 indicate?
Theproject is 90% over budget.
The
project is 90% over budget.
Theproject is 10% behind schedule.
project is 10% behind schedule.
Theproject is 10% ahead of schedule.
project is 10% ahead of schedule.
Theproject is 90% complete.
project is 90% complete.