Both task B (4 weeks) and task C (3 weeks) will start after task A (3 weeks) fin...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Both task B (4 weeks) and task C (3 weeks) will start after task A (3 weeks) finished. If task D (4 weeks) will start after both tasks B and C finished, what is the duration of the project if it starts from time 0?