The Kruger National Park enters into an agreement with Easy Thatch in terms of which Easy Thatch will thatch the roofs of three hundred newly built bungalows. Their contract stipulates that the bungalows must be ready before 15 September in time for the commencement of the European holiday season, which starts on 1 October. Easy Thatch only finishes the work at the end of November, and most of the new thatch roofs leak when it rains. The bungalows are not thatched by the agreed time because Easy Thatch did not order enough grass in time and therefore spent weeks waiting for their suppliers to deliver enough grass. Which form/s of breach of contract occurred in this set of facts?