Which sequence best reflects a correct managerial use of a risk matrix?
Rank risks only by revenue impact
Decide mitigation first → Then assess impact
Define context and risk appetite → Identify risks → Assess impact and probability → Map and prioritize → Decide treatment and monitor
Identify risks → Transfer all high risks → Monitor only