✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
ImagineX Builders Limited (ImagineX) is a company engaged in developing sustainable greenhouse residential and commercial premises. It wanted to do the outdoor lighting for a new project through solar power. For this, it commissioned Future Forward Energy Limited (FFEL) to develop the complete system, including procuring and installing solar panels on the rooftop, installing batteries and switches, and complete wiring for the system. A fully functional outdoor lighting was to be handed over to ImagineX.
The entire value of the contract was Rs. 5 Crore. The contract provided a date by which the completed functional outdoor lighting was to be handed over to ImagineX.
FFEL delayed handing over of the completed outdoor lighting by 25 days. FFEL raised an invoice for the contract value, which ImagineX paid. The contract had the following clause on damages:
Clause 8: For a delay in handing over a completed functional outdoor lighting, FFEL will be liable to pay a penalty at the rate of 0.5% per day of delay of the contract value.
ImagineX claimed damages for the 25 days of delay in handing over of the outdoor lighting according to the clause. FFEL counters the claim. It contends that the clause uses the word ‘penalty’, declaring the intention of ImagineX to penalise FFEL. Thus, the clause is a penalty and should be declared non-binding. Is clause 8 penal?