The following Gantt chart depicts a project that has two paths: path ACDFH (i.e., the critical path) and path BEG. Assume that activity B must be completed before activity D, activity E must be completed before activity G, and activity G must be completed before activity H. After resource levelling, what is the maximum number of employees required throughout the duration of the project?