Preliminaries section in a BQ is normally the last section to be priced because_____.
it is the easiest section to be priced.
it is the most difficult section to be priced.
many items of the preliminaries section cannot be priced until the full scope of work is known.
it needs to be priced by the top management in the tender adjudication meeting.