In MRP, if an item has a lead time of 2 weeks and is required in week 6, in whic...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

In MRP, if an item has a lead time of 2 weeks and is required in week 6, in which one of the following weeks should the order be placed?

0%
0%
0%
100%