You are required to report to the relevant stakeholders on the project progress 18 weeks into the project. Below is the current progress at the end of Week 18. Conduct the EVM analysis and answer the questions below.
Activity
|
% Complete
|
Actual Cost (RM)
|
A
|
100%
|
60,000
|
B
|
100%
|
45,000
|
C
|
100%
|
85,000
|
D
|
100%
|
85,000
|
E
|
100%
|
125,000
|
F
|
80%
|
130,000
|
G
|
100%
|
75,000
|
H
|
60%
|
120,000
|
I
|
0%
|
0
|
J
|
25%
|
60,000
|
K
|
0%
|
0
|
L
|
0%
|
0
|
M
|
0%
|
0
|
Which activity is currently behind the planned schedule the most?