You are required to report to the relevant stakeholders on

the project progress 18 weeks into the project. Below is the current progress

at the end of Week 18. Conduct the EVM analysis and answer the questions below.

Activity

% Complete

Actual Cost (RM)

A

100%

60,000

B

100%

45,000

C

100%

85,000

D

100%

85,000

E

100%

125,000

F

80%

130,000

G

100%

75,000

H

60%

120,000

I

0%

0

J

25%

60,000

K

0%

0

L

0%

0

M

0%

0

Which activity is currently behind the planned schedule the

most?