Consider the following three-step assembly operation with quality problems. All...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Consider the following three-step assembly operation with quality problems. All steps are staffed by a dedicated employee (so that the different steps can be performed in parallel).

The first step has a processing time of 7 minutes per unit. The second step has a processing time of 6 minutes per unit.  The third step has a processing time of 5 minutes per unit. 

With a 40% probability, the units coming out of the third step have to be reworked. In that case, the operations at the second and third steps are repeated. 

You can assume that rework always succeeds (i.e. a unit going through the rework loop will always work after the third step) and the processing times for units in rework are the same as for regular units.

Which step is the bottleneck of the process? 

100%
0%
0%
More questions like this

Want instant access to all verified answers on moodle.essec.fr?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!

Browser

Add to Chrome