The primary EEFs used as inputs to the Estimate-Activity-Durations process are the duration estimating databases, productivity metrics, and team members' locations. The primary organizational process assets used as inputs to this process are historical duration information, scheduling methods, estimated policies, project calendars, and the lessons learned repository.