Add to Chrome
✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
The master production schedule (MPS) is primarily a … planning function, whereas PAC is a … controlling tool.
short-term; long-term
medium-term; short-term
long-term; medium-term
short-term; medium-term