19. Which two statements are CORRECT about the minimum requirements for applyi...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

19. Which two statements are CORRECT

about the minimum requirements for applying the 

change theme?

1. Identified issues must be assessed

for their impact on the business justification for the 

project.

2. Project issues must be captured,

examined and managed throughout the project 

lifecycle.

3. The actual status of products must

be verified to ensure that this matches the 

authorized state.

4. A budget must be established to pay

for requests for change and their analysis.