✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
Determine the CYCLE (duration budget)
Assumptions: a. 5 employees, b. demanded production A=20 pcs, B=20 pcs, C=20 pcs and D=20 pcs.
| A | B | C | D |
| 12 | 11 | 12 | 31 |
| 3 | 7 | 11 | 7 |
| 4 | 8 | 1 | 5 |
| 11 | 11 | 6 | 4 |
| 12 | 2 | 7 | 2 |