Determine the CYCLE (duration budget) Assumptions:   a.  5 employees,  b . de...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Determine the CYCLE (duration budget)

Assumptions:  a. 5 employees, b. demanded production A=20 pcs, B=20 pcs, C=20 pcs and D=20 pcs.

ABCD
12111231
37117
4815
111164
12272

The cycle time is (choose correct answer):

0%
0%
0%
100%