Government and industry standards, as well as communication channels, are the leading enterprise environmental factors (EEFs) used as inputs in the Develop-Schedule process. The primary organizational process assets used as inputs to this process are the scheduling method, which includes the policies governing the schedule and its maintenance, and the project calendars.