What is the critical path
allows you to determine the full reserve of time, that is, the difference between the late and early work completion dates
it is the maximum duration of the complete path in the network, that is, it determines the shortest total duration of work on the project as a whole. The works that lie on this path have a name - critical;
allows to determine the term of completion of works
the shortest path in the network