What are the two primary artifacts resultingfrom a sprint planning meeting?
What are the two primary artifacts resulting
from a sprint planning meeting?
A requirements documents and a testplan
A requirements documents and a test
plan
A test plan and a product backlog
A requirements documents and a product backlog
A sprint backlog and sprint goal