I have a redwarning on my resource on the lines 6, 7, 8.What is the issue?
I have a red
warning on my resource on the lines 6, 7, 8.
What is the issue?
Luis is notproperly setup in the resource section of the software.
Luis is not
properly setup in the resource section of the software.
Luis is correctly assigned but he does not exist on the system. I must create it.
Luis is over assigned. He has days off these days setup on the system.
Luis is over assigned. I should assign him only on the line 6
Luis is over assigned. I should assign him only on the lines 7 and 8.