After completing a digital transformation project aimed at streamlining outpatient services, a project manager is asked to develop a final report as part of the project closing phase. The project experienced multiple scope changes and realignments with organizational strategy during execution. Leadership expects the report to serve as a strategic reference for future initiatives.
Which approach best ensures that the project report becomes a valuable organizational learning asset rather than a mere archive?