logo

Crowdly

The Advanced Rural Water & Energy Sustainability Project An engineering cons...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The Advanced Rural Water & Energy

Sustainability Project

An

engineering consortium that you work for is tasked with a comprehensive project

in a remote rural region, focusing on water purification, renewable energy, and

sustainable waste management. The project aims to provide clean water, reliable

energy, and improve sanitation. You are assigned as the project manager to

oversee the project’s progress. Based on the stakeholder’s engagement and

previous projects, you have estimated the relevant costs, duration as well

interdependencies of each activity as summarised in the table below.

 

Activity

Description

 Predecessor(s) 

 Duration (Weeks) 

 Planned Cost (RM)

A

Community Needs & Site Assessment

-

4

60,000

B

Water Source Analysis & Testing

A

3

40,000

C

Solar Panel System Design

A

5

80,000

D

Water Purification System Design

B

6

90,000

E

Solar Panel Procurement & Delivery

C

4

120,000

F

Purification System Procurement

D

5

150,000

G

Biogas Digester Design

A

4

70,000

H

Solar Panel System Installation

E

7

180,000

I

Water Purification System Installation

F

6

160,000

J

Biogas Digester Construction

G

8

200,000

K

Integrated System Wiring & Control

H, I, J

5

100,000

L

Water & Energy Quality Validation

K

3

60,000

M

Community Training & Handover

L

4

80,000

 

Prepare a network diagram and answer the following questions.

What is the total duration of the project (in weeks). Insert

numeric value in the box below

More questions like this

Want instant access to all verified answers on learning.monash.edu?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!