The Advanced Rural Water & Energy Sustainability Project
An engineering consortium that you work for is tasked with a comprehensive project in a remote rural region, focusing on water purification, renewable energy, and sustainable waste management. The project aims to provide clean water, reliable energy, and improve sanitation. You are assigned as the project manager to oversee the project’s progress. Based on the stakeholder’s engagement and previous projects, you have estimated the relevant costs, duration as well interdependencies of each activity as summarised in the table below.
Activity
|
Description
|
Predecessor(s)
|
Duration (Weeks)
|
Planned Cost (RM)
|
A
|
Community Needs & Site Assessment
|
-
|
4
|
60,000
|
B
|
Water Source Analysis & Testing
|
A
|
3
|
40,000
|
C
|
Solar Panel System Design
|
A
|
5
|
80,000
|
D
|
Water Purification System Design
|
B
|
6
|
90,000
|
E
|
Solar Panel Procurement & Delivery
|
C
|
4
|
120,000
|
F
|
Purification System Procurement
|
D
|
5
|
150,000
|
G
|
Biogas Digester Design
|
A
|
4
|
70,000
|
H
|
Solar Panel System Installation
|
E
|
7
|
180,000
|
I
|
Water Purification System Installation
|
F
|
6
|
160,000
|
J
|
Biogas Digester Construction
|
G
|
8
|
200,000
|
K
|
Integrated System Wiring & Control
|
H, I, J
|
5
|
100,000
|
L
|
Water & Energy Quality Validation
|
K
|
3
|
60,000
|
M
|
Community Training & Handover
|
L
|
4
|
80,000
|
Prepare a network diagram and answer the following questions.
What is the total duration of the project (in weeks). Insert numeric value in the box below