Identify the correct statement/s from the following:
Statement 1: The scope statement reflects a project team’s best at creating the documentation and approval of all important project parameters prior to proceeding to the development phase.
Statement 2: Establishing a work breakdown structure is not important in the scope statement
Statement 3: The scope baseline is a document that provides a summary description of each component of the project’s goal.