Within the following list select the true statements.
(Multiple answers expected)
100% of the work should be included.
The WBS should NOT include anywork that falls outside of the scope of the project .
The 100% rule apply at all levels within the hierarchy.
The WBS shall be set sequencially in chronological order
The 100% shall apply to the activity level.