Consider the following activity-on-node diagram. Which of the following is/are true? (select all that apply)
Task D and Task E will run at the same time.
Task G can start immediately once Task D has finished.
Task B and Task C can both start at the same time.
Task H can start before task F.
Task I will have no float.
Task G will have no float.