A workshop has only 3,000 direct labour hours available next month due to staff ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A workshop has only 3,000 direct labour hours available next month due to staff shortages. Demand is effectively unlimited.

The workshop can produce Product A or Product B with the following contribution and labour requirements:

• Product A: contribution £8 per unit; 2 labour hours per unit

• Product B: contribution £9 per unit; 3 labour hours per unit

To maximise profit, which product should be prioritised given labour hours are the limiting factor?

❌
❌
✅
❌