The primary inputs to the Perform-Quantitative-Risk-Analysis process are the ris...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The primary inputs to the Perform-Quantitative-Risk-Analysis process are the risk management plan, scope baseline, schedule baseline, cost baseline, assumption log, basis of estimates, cost estimates, cost forecasts, duration estimates, milestone list, resource requirements, risk register, and schedule forecasts.