A project manager is using COCOMO (Constructive Cost Model) to estimate effort f...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A project manager is using COCOMO (Constructive Cost Model) to estimate effort for a new e-commerce website. The estimated lines of code is 50,000 (50 KLOC) and the project is classified as "Semi-detached" mode. If the effort equation is E = 3.0 × (KLOC)^1.12, approximately how many person-months of effort are required?

100%
0%
0%
0%