The Control-Scope process monitors the project status and the project and produc...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The Control-Scope process monitors the project status and the project and product scopes and manages changes to the scope baseline. It also ensures that all change requests and their corrective actions are processed through the Perform-Integrated-Change-Control process.