A project contains 64 tasks, and 15 milestones

The task 23 belong to the critical path but it is located rigth after an important decision milestone.

The project duration is:  123 days.

Due to a technical issue the duration of the task 23 is increased from 23 to 25 days.

Without any further change, the project duration will be extended by how many days? 