logo

Crowdly

The principal subsidiaries of the project management plan used as inputs to the ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The principal subsidiaries of the project management plan used as inputs to the Estimate-Activity-Durations are the schedule management plan, scope baseline, activity attributes, activity list, assumption log, lessons learned register, milestone list, project team assignments, resource requirements, risk register, resource calendars, and resource breakdown structure (RBS).
100%
0%
More questions like this

Want instant access to all verified answers on elearn.just.edu.jo?

Get Unlimited Answers To Exam Questions - Install Crowdly Extension Now!