The principal subsidiaries of the project management plan used as inputs to the Estimate-Activity-Durations are the schedule management plan, scope baseline, activity attributes, activity list, assumption log, lessons learned register, milestone list, project team assignments, resource requirements, risk register, resource calendars, and resource breakdown structure (RBS).