At a production level of 5 600 units a project has total costs of R89 000. The v...
✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.
At a production level of 5 600 units a project has total costs of R89 000. The variable cost per unit is R11.20. What is the amount of the total fixed costs if the production level is increased to 6 100 units without increasing the total fixed assets?