Under the unamended AS4000 – 1997 General Conditions of Contract, outline the Contractor’s contractual rights in the event of delays caused by:
a. the Contractor's error in ordering required materials
(10 marks)
b. the Principal’s late issue of production information
(5 marks)
c.
(5 marks)