Assigning jobs to machines A workshop has five jobs to run today. Each job runs ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Assigning jobs to machines

A workshop has five jobs to run today. Each job runs on exactly one machine, each machine can run only a limited number of jobs in a day, and each job needs a machine with the right tooling. The workshop wants to run as many jobs as possible.

machinemaximum number of jobs
m11
m21
m33
machinejobs it can take
m1j1
m2j2, j4, j5
m3j1, j3

Someone proposes to solve this with a flow network. It has a source s, one vertex per machine, one vertex per job and a sink t, with these edges:

edgeshow the proposal defines them
source edgesfrom the source to each machine, with capacity equal to that machine's own limit
middle edgesfrom each machine to each job it is allowed to take, with capacity 1
sink edgesfrom each job to the sink, with capacity equal to the number of machines that could take that job

They compute a maximum flow in it and report its value as the number of jobs that can be covered.

The proposal is wrong: on the instance above it reports a number that is too large. Answer all four parts.

  1. What is the value of a maximum flow in the proposed network on this instance? Describe a flow that achieves it.
  2. What is the true answer, i.e. the largest number of jobs that can be covered? Give an assignment that achieves it.
  3. Which requirement of the original problem does the proposed network fail to enforce? Explain exactly how the flow you gave in part 1 breaks that requirement.
  4. Repair the construction, and explain why your repair enforces the requirement.

Write in plain text. You may describe edges as s -> v1 and so on.