A team's average lead time is 20 days: 8 days waiting in backlog, 3 days develop...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A team's average lead time is 20 days: 8 days waiting in backlog, 3 days development, 2 days code review, 5 days testing, 2 days deployment approval. Which intervention would MOST reduce lead time?

100%
0%
0%
0%