Scenario:
You are managing a project to renovate an old historic building into a modern art gallery. The project has several stakeholders, including the city council, preservation society, and local community members. The city council has granted permission for the renovation, but the preservation society is very concerned about preserving the building’s historical integrity. They have expressed strong opposition to any changes that they deem disruptive to the building’s original design.
Question:
Based on the stakeholder matrix discussed in the lecture, which quadrant would the preservation society MOST likely fall into?