A residential development has 2 years construction period. The total development...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

A residential development has 2 years construction period. The total development cost of this project is $23,000,000 and the GDV of the project is $48,000,000. Assuming the developer’s margin is 15% of the GDV, calculate the land value.

Just provide the final answer.