The Process P1, P2, P3, P4 and P5 arrive at the same time to the CPU. The Burst Time of each process is given in the Table.
Using ROUND ROBIN scheduling algorithm, Considering the Time Quantum (TQ) of 4 units of time, AND Context Switch Time is 1 unit. Construct the Ready Queue.
Solve the numerical calculations and answer the below questions. (1X5 = 5 Marks)
Process | Burst Time (BT) |
P1 | 7 |
P2 | 2 |
P3 | 11 |
P4 | 6 |
P5 | 3 |
1. What is the Completion Time of the Process P4 ?
5. Total number of times "Context Switching" occurs?