The per-unit standard for direct labour is 4 direct labour hours at $12 per hour...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The per-unit standard for direct labour is 4 direct labour hours at $12 per hour. In producing 1,200 units last year, the actual direct labour cost was $51,200 for 4,000 direct labour hours worked, the direct labour efficiency variance is therefore

0%
0%
100%
0%