The primary inputs to the Plan-Cost-Management process include the project chart...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

The primary inputs to the Plan-Cost-Management process include the project charter, project management plan/subsidiaries, EEFs, and OPAFs.