Read the following statements and identify the correct ones: I. The risk is ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

Read the following statements and identify the correct

ones:

I. The risk is highest in the

earliest phase of the project life cycle.

II. Opportunity emerges from

favourable project circumstances and risk from unfavourable events.

III. As risk decreases in the

project life cycle, opportunities increase.