Contractors' pricing for prime cost sums (PC sums) in a tender would include all of the following except ________.
Special builder's work related to nominated subcontracts in a tender.
Profit based on nominated subcontractor's contract sum.
Wastage factor for materials in nominated suppliers' contract.
General attendance for temporary services accessible by nominated subcontractors and suppliers.