Arnica Limited is constructing an amusement park on the beachfront. Construction of the park had to be suspended thrice, details of which are as follows: | ||
Reasons for periods during which construction was suspended: | ||
| Date suspended: | Date resumed: | |
| First period of suspension of construction – period A | ||
• Construction was delayed for almost 1 month because the cement work involved in the construction of the various foundations had to cure before construction could commence. | 02 February 2024 | 05 March 2024 |
| Second period of suspension of construction – period B | ||
• Construction was delayed for almost 2 months after a minor earthquake on 20 March 20X4 caused certain tectonic plates to tilt in a way that caused underground water to pool. This water had to be drained from the construction site before construction could continue. | 20 March 2024 | 15 June 2024 |
| Third period of suspension of construction – period C | ||
• Construction was delayed for almost 2 months due to the anticipated seasonal monsoons during most of September and October 2024. | 05 September 2024 | 27 October 2024 |