Arnica Limited is constructing an amusement park on the

beachfront. Construction of the park had to be suspended thrice, details of

which are as follows:

Reasons

for periods during which construction was suspended:

 Date suspended:Date resumed:
First period of suspension of construction – period A

Construction was delayed for almost 1 month because the cement work involved

in the construction of the various foundations had to cure before

construction could commence.

02 February 202405 March 2024
Second period of suspension of construction – period B

Construction was delayed for almost 2 months after a minor earthquake on 20

March 20X4 caused certain tectonic plates to tilt in a way that caused

underground water to pool. This water had to be drained from the construction

site before construction could continue.

20 March 202415 June 2024
Third period of suspension of construction – period C

Construction was delayed for almost 2 months due to the anticipated seasonal

monsoons during most of September and October 2024.

05 September 202427 October 2024

(Choose once correct option only)