You are managing a smart home automation project. The project includes the following tasks:
Finish-to-Finish (FF) – Task C can only finish when Task B finishes.
Start-to-Start (SS) – Task C can start as soon as Task B starts.
Finish-to-Start (FS) – Task C cannot start until Task B is completed.
Start-to-Finish (SF) – Task B must start for Task C to be completed.