Company X uses a process costing system and computes cost using the weighted average. Inspection point is at 56% of the production process. Company X presented the following information:
Assignment of costs
| |
Costs before adding normal spoilage
|
$882,250
|
Normal spoilage on good completed units
|
$56,425
|
Total cost of good units and transferred out
|
$938,675
|
Abnormal spoilage
|
$33,855
|
EWIP before normal spoilage
|
$344,500
|
Normal spoilage on EWIP
|
$22,570
|
EWIP
|
$367,070
|
Total costs accounted for
|
$1,339,600
|
Which of the following is TRUE