Please select the correct process of CFA piling works.
Drilling --> Design depth is reached --> Auger is withdrawn, while concreting takes place --> Concreting reaches the ground level --> Reinforcement cage is put in place
Drilling --> Design depth is reached --> Reinforcement cage is put in place --> Auger is withdrawn, while concreting takes place --> Concreting reaches the ground level
Drilling --> Reinforcement cage is put in place --> Design depth is reached --> Auger is withdrawn, while concreting takes place --> Concreting reaches the ground level
Concreting reaches the ground level --> Reinforcement cage is put in place --> Drilling --> Design depth is reached --> Auger is withdrawn, while concreting takes place
Auger is withdrawn, while concreting takes place --> Concreting reaches the ground level --> Drilling --> Design depth is reached --> Reinforcement cage is put in place