During sprint planning for a healthcare management system, the development team ...

✅ The verified answer to this question is available below. Our community-reviewed solutions help you understand the material better.

During sprint planning for a healthcare management system, the development team estimated User Story A as 8 story points and User Story B as 13 story points. The team's velocity from the last three sprints averaged 40 story points per sprint. How should the Scrum Master handle sprint commitment if there are 5 more stories totaling 25 points?